On April 3, 2026, USDA issued a final rule that revised the departmental NEPA regulations and removed and reserved seven agency-specific NEPA regulations, with limited portions (e.g. categorical exclusions and emergency action provisions) moved to and republished in the departmental NEPA regulations at 7 CFR Subtitle A Part 1b (hereinafter 7 CFR 1b).
Determining NEPA Applies
NEPA does not apply to a proposal when:
- The proposal is not a “major Federal action”. The terms “major” and “Federal action,” each have independent force. NEPA applies only when both of these two criteria are met. Such a determination is inherently bound up in the facts and circumstances of each individual situation, and is thus reserved to the judgment of a USDA subcomponent in each instance;
- The proposal or decision is exempted from NEPA by law;
- The proposal or decision do not result in final Federal agency action under the Administrative Procedure Act, see 5 U.S.C. 704, or other relevant statute that also includes a finality requirement;
- In circumstances where Congress, by statute, has prescribed decisional criteria with sufficient completeness and precision such that a Federal agency retains no residual discretion to alter its action based on the consideration of environmental factors, then that function of a USDA subcomponent is nondiscretionary within the meaning of NEPA section 106(a)(4) and/or section 111(10)(B)(vii) (42 U.S.C. 4336(a)(4) and 4336e(10)(B)(vii), respectively), and NEPA does not apply to the action in question;
- Compliance with NEPA would clearly and fundamentally conflict with the requirements of another provision of law; or
- The proposal is an action for which another statute's requirements serve the function of the Federal agency's compliance with the Act.
(7 CFR 1b.2(e))
Levels of NEPA Review
There are three levels of NEPA review: categorical exclusions (CEs), environmental assessments (EAs), and environmental impact statements (EISs). CEs are the least complex level of review, while EISs are the most complex.
LEVEL OF NEPA | WHEN TO USE | FINDING/DECISION DOCUMENT |
|---|---|---|
Environmental Impact Statement | Reasonably foreseeable significant effects anticipated | Record of Decision |
Environmental Assessment | No reasonably foreseeable significant effects anticipated, or uncertain | Finding of No Significant Impact (FONSI) |
Categorical Exclusion | Actions fit a category/ies and there are no extraordinary circumstances | Finding of Applicability & No Extraordinary Circumstance (FANEC)* *If a FANEC is required |
Categorical Exclusions (CEs)
USDA’s CEs can be found in 7 CFR 1b.4(c) and 7 CFR 1b.4(d). CEs can only be used for those actions for which they apply and there must be no extraordinary circumstances. The responsible official must reach a Finding of Applicability and No Extraordinary Circumstance (FANEC) to use a CE. CEs listed in 7 CFR 1b.4(c) are not required to document this finding, while CEs listed in 7 CFR 1b.4(d) do require the FANEC to be documented.
USDA has also adopted CEs from other agencies, as permitted by NEPA section 109, 42 U.S.C. 4336c. To learn more, please view a list of categorical exclusions adopted by USDA from other federal agencies (PDF, 240 KB).
Environmental Assessments (EAs)
If a CE does not apply and there are no reasonably foreseeable significant impacts on the quality of the human environment, an EA will be completed (7 CFR 1b.5). An EA may also be completed if the significance of the impact is unknown. EAs conclude with a Finding of No Significant Impact (FONSI) (7 CFR 1b.6). The FONSI may be included in the same document as the EA. If a FONSI cannot be reached, then an EIS is completed.
The text of an environmental assessment will not exceed 75 pages (NEPA section 107(e)(2), 42 U.S.C. 4336a(e)(2)), not including citations or appendices.
Environmental Impact Statements (EISs)
An EIS is completed when there is a reasonably foreseeable significant impact on the quality of the human environment (7 CFR 1b.7). EISs conclude with a Record of Decision (ROD) (7 CFR 1b.8). The ROD may be included in the same document as the EIS.
The text of an EIS will not exceed 150 pages (NEPA section 107(e)(1)(A), 42 U.S.C. 4336a(e)(1)(A)), unless the EIS is for a proposal of extraordinary complexity and then it will not exceed 300 pages (NEPA section 107(e)(1)(B), 42 U.S.C. 4336a(e)(1)(B)), not including any citations or appendices.
Templates
The following templates provide examples of how a FANEC, EA and FONSI, or EIS and ROD could be documented.
- USDA FANEC Template (DOCX, 94.0 KB)
- USDA EA and FONSI Template (DOCX, 178 KB)
- USDA EIS and ROD Template (DOCX, 186 KB)
For additional information about USDA NEPA, email SM.OSEC.CERPO@usda.gov.